Construction updates
Overview of new construction
We would like to keep you informed about the construction work progress per period.
July 2025 Highest point & merging new hotel wing
We are proud to announce that the highest point of the construction has been reached. Our new hotel wing is now fully visible, giving Van der Valk Groningen-Hoogkerk a beautiful new appearance.
In the coming period, we will continue to work intensively on the completion and furnishing. Additionally, the new hotel wing will finally be connected to the rest of the hotel! With this expansion, we will soon offer even more space for our guests to enjoy comfort, hospitality, and experience.
A special moment to reflect on. Thanks to all involved for their dedication and craftsmanship in making this milestone possible.
March 2025
In March, we expect to reach a significant milestone: the installation of the first floor. From that moment on, we will literally build up step by step!
February 2025
In February, the focus is on the preparatory work for the high-rise building. The floor is being installed and the first outlines of the ground floor are becoming visible. The hotel is really starting to take shape!
Keep following our construction updates for the latest developments!
Previous Construction Updates - 2024
July 2024 - Preparations, pile driving, demolition of facade, and water drainage works.
August/September 2024 - The heathland clearance and demolition work have been completed. At the moment, preparations are being made for the foundation.
30th September 2024
The reinforcement of the foundation has been completed and the pedestals have been placed. These pedestals form an extra strong structure in the foundation, distributing the load of the overlying elements, such as walls and floors, evenly over the ground.
October 7, 2024
The installation of the crawl spaces has started. This involves laying down the sewer, rainwater drainage, air ducts, and power cables. Everything is being prepared so that the floor can be laid.
October 11, 2024
The swimming pool has been installed. This pool, which was delivered ready-made, is made of plastic and includes a bench and a small staircase. The luxury finishing will be done at a later stage of the construction.
October 30, 2024
Today, the insulated hollow core slabs have been placed on the foundation. The next step is to install the edge formwork, after which next week the pouring of the key joints and a structural concrete topping of 7 cm will begin. By the end of the week, the ground floor slab will be fully structurally completed.
November 18, 2024
From week 47 until the end of the year, the site leads will be installed.
January 2025
During weeks 1 to 3, the tower crane will be installed. This crane is essential for the construction of the hotel tower. The lower parts, such as the wellness area and the meeting rooms, will be built using mobile cranes. The tower crane has a height of 40 meters, while our tower will be approximately 26 meters tall.